Following up to the initial Master Plan and Phase I of its implementation, the scope of the second phase of the Northern Water Berthoud Campus Expansion extensively renovates the primary office building on the campus, reconfigures its board room, adds a new secure lobby, and a three-story office wing. It also expands parking areas and demonstration gardens.
Lastly, a covered outdoor meeting area with restrooms was added to assist with educational programs and internal conference needs.
The final phase of the master plan includes mail, maintenance and storage facilities. All buildings were designed with similar building forms and materials for a unified feel. Care was taken to design efficient vehicular and pedestrian connections from building to building and demonstration gardens were incorporated throughout the landscape to create a park-like feel throughout.
LOCATION:
Berthoud, CO
CLIENT:
Northern Water
SCOPE:
37,400 SF New, 51,800 SF Renovation, 3,000 SF Pavilion
COST:
$34.4 Million
COMPLETED:
2025